Estonia Opens Its Largest Solar Park as Midday Power Prices Fall to Zero
Estonia's largest solar park has opened in Risti, in Lääne County in the west of the country, ERR News reported on 21 November. Built by the renewable energy company Sunly at a cost of €125 million, the 244-megawatt site has enough capacity to cover the annual electricity consumption of roughly 90,000 households.
The park spans 270 hectares and holds 340,000 panels, making it the second largest solar facility in the Baltic states. Sunly's chief executive Priit Lepasepp put the 90,000 households in context by noting that the figure equals the combined populations of Tartu, Narva and Pärnu.

The opening is only the first phase. A substation is already complete and construction of a battery park has begun with Rolls-Royce, while a wind farm and a large data centre are planned for the same site. Lääne-Nigula's mayor, Janno Randmaa, welcomed the payments the project will make to the local community and the technology jobs expected to follow.
The design reflects a sharp change in Estonia's power market. Solar capacity has grown so quickly that installed panels now exceed the country's annual peak demand, and on sunny summer days this has pushed midday electricity prices to zero. When every solar farm produces at the same time, each extra megawatt-hour earns less, a pattern often described as price cannibalisation.
Lepasepp told ERR that standalone solar or wind farms are no longer viable in these conditions. Sunly plans to earn its revenue in other ways: by providing frequency regulation to keep the grid stable, and by storing cheap daytime power in batteries and selling it later when gas-fired electricity is expensive. On-site consumers such as the planned data centre add a further buyer for power that would otherwise be sold at little or no value.
Sunly is not alone in reaching that conclusion. ERR reported that Enefit, the state-owned rival, has paused its standalone solar projects. Johann-Gustav Lend, who heads Baltic business development at the company, agreed that future sites will need hybrid set-ups paired with large on-site power consumers.
For Estonia, which has been moving away from oil-shale power, Risti shows both how far solar has come and where its limits now lie. Building panels has become the easy part. Storing their output, balancing the grid and finding buyers at the right hour are now what decide whether the next project goes ahead.
Why it matters
Zero midday prices sound like good news for consumers, but they can stall investment if projects cannot earn enough to repay their costs. Pairing solar with batteries, wind and on-site users is how developers in Estonia are keeping clean power bankable.

Comments