KAUST Coating Could Help Saudi Power Lines Carry More Current in Extreme Heat
Saudi Arabia's electricity network faces a problem that grows worse exactly when demand peaks. On the hottest afternoons, when air-conditioning pushes consumption up, overhead transmission lines heat up and lose some of their ability to carry current. Researchers at King Abdullah University of Science and Technology (KAUST) say a new coating could ease that bottleneck, according to a report in Arab News on 20 November.
The coating is a silicone-based polymer containing boron nitride particles. It is designed to do three things at once: reflect sunlight, shed heat as infrared radiation, and let the heat generated inside the conductor escape. Kai Xu, a postdoctoral fellow at KAUST, told the newspaper that overhead lines are heated both by direct sun and by the electrical current flowing through them, and that during extreme heat their ability to release that heat is limited, so conductor temperatures rise.

That matters because temperature sets the practical ceiling on how much a line can carry. Saudi electrical engineer Nada Battyour explained to Arab News that as a conductor heats up its resistance increases, which raises losses. Heat can also make lines sag and age faster, and extreme temperatures reduce ampacity, the maximum current a line can safely carry.
The headline figure comes from modelling. Qiaoqiang Gan, professor of materials science and applied physics at KAUST, said that under extreme summer conditions in Riyadh the coating could raise the current-carrying capacity of thermally constrained overhead conductors by up to 18.3 percent compared with conventional insulated cables. He said the extra capacity in existing infrastructure could defer some new construction, reduce material use and ease bottlenecks.
Early durability tests are encouraging. According to Xu, the coating kept its optical properties after 1,000 abrasion cycles and 240 hours of accelerated ultraviolet ageing, and the team has also tested how it copes with dust and salt spray, both relevant in a desert and coastal climate.
The researchers are careful about what they have not yet shown. They have not established verified annual energy savings or carbon reductions for a full-scale operating network, and Xu said these would depend on conductor type, operating current, line length, climate and the generation mix. Gan also described conductor cooling as one complementary tool rather than a complete answer, alongside grid stability, storage and network planning.
There is a clear link to the energy transition. Battyour said extra line capacity could help integrate solar power, particularly on heavily loaded lines already close to their thermal limits. As more large solar plants connect to the grid, the lines that carry their output at midday are often the same ones under the greatest heat stress.
The next step is moving from the laboratory towards the network. Gan said the team had held meetings with Saudi Electricity Co. about its cooling technologies, but that further development and practical deployment are still needed, and that the team is focusing on industry standards, technical requirements and market qualification criteria.
Why it matters
Hot countries are building solar faster than they can build new transmission lines. If a coating can safely unlock spare capacity in wires that already exist, it could become one of the cheaper ways to move clean power at peak times, provided field trials confirm what the models suggest.