Mauritius Weighs 11 Solar Projects of Nearly 80 MW as Renewables Target Moves to 2035
Mauritius could add a sizeable block of solar power to its grid if eleven projects now before the regulator are approved. The Utility Regulatory Authority (URA) opened a public consultation on 16 November on licence applications for projects totalling 78.8 MWdc, or about 57 MWac, News Moris reported on 18 November, citing Defi Media.
The applications come mostly from industrial and commercial companies. They include two projects by the Mauritius Freeport Development Company at Mer Rouge, two by Tianli Spinning at Petite-Rivière, two by Gamma Materials at Gros-Cailloux, and projects by Compagnie Mauricienne de Textile and RT Knits at Pointe-aux-Sables, Avipro and Les Moulins de la Concorde at Amaury, and Stor'sun 2 at Trou-d'Eau-Douce. The Stor'sun 2 project, the largest at 16.7 MWdc, is one of two applications that include battery storage.

The scale is significant for a small island grid. According to figures from the Central Electricity Board cited in the report, installed capacity was roughly 880 MW at the end of 2024, so 80 MW would represent about 9% of the fleet. The newspaper says approving all eleven would raise installed solar capacity by more than 20%. Under the Electricity Act 2005, members of the public can lodge written, reasoned objections with the URA within 14 days of the final publication of the notice.
The wave of applications follows a reset of national ambition. On 28 October, Energy Minister Patrick Assirvaden announced that the target of generating 60% of electricity from renewables had been moved from 2030 to 2035, saying he preferred realistic targets backed by projects that come to fruition over big promises that remain on paper. He said the renewable share of output had fallen from about 21% to 17% between 2014 and 2024. As of 15 October, Mauritius had nearly 395 MW of renewable capacity, including nearly 198 MW of solar.
The pipeline beyond the eleven licences is substantial. The minister listed around 54 MW from the CNIS programme due by December, a 15 MW solar station at Le Val, connections for Freeport and CMT, and four battery-backed solar projects totalling 60 MW, the first 10 MW due in December and the rest in early 2027. Tenders are being evaluated for ten 10 MW projects and three 40 MW projects, and a 15 MW floating solar scheme and a wind farm are being designed.
Storage will be important. Demand on the island peaks between 6 pm and 9 pm in summer, after the sun has set, and the government has encouraged electric vehicle owners to charge after 9 pm. The Mauritius Meteorological Services has also warned that a strong El Niño could bring a particularly hot summer, adding pressure on electricity and water.
Why it matters
After admitting that its 2030 goal was out of reach, Mauritius now needs to show that the new 2035 date is backed by projects that actually connect. Eleven licences adding more than a fifth to installed solar capacity would be a concrete step, especially if storage helps cover the evening peak.