Writer: Stephen Abela Stephen Abela

Servers and Sockets: What the Dutch Data Centre Boom Means for Europe's Power Grids

When Statistics Netherlands (CBS) reported on 18 November that data centres had used 5% of the country's electricity in 2025, the number confirmed a trend that grid operators, city councils and climate campaigners had been tracking for years. In 2017 the share was 1.5%. It has risen every year since, and it is now high enough to matter for a national energy system that is already short of grid capacity.


This Research Desk piece looks beyond the headline: what the figures say, how the Netherlands compares with Ireland and the rest of Europe, how governments are trying to manage the demand, and what to watch as artificial intelligence pushes consumption higher.

Servers and Sockets: What the Dutch Data Centre Boom Means for Europe's Power Grids - Sustainable Development Goals


What the Dutch figures show


According to CBS, about 200 data centres were supplied with 5,664 GWh of electricity in 2025, 5.0% of national consumption and about 12% more than in 2024. The 2025 figures are provisional. The year-by-year series shows steady growth: 2.1% in 2018, 2.8% in 2020, 4.0% in 2022 and 4.6% in 2024.


Demand is highly concentrated. Around 50 large centres, each using at least 10 GWh a year, accounted for 5,289 GWh in 2025, up from 4,662 GWh a year earlier. Smaller centres used 374 GWh, slightly less than in 2024. CBS describes the large centres' share as about 90 percent; on the published numbers it is a little over 93%. The statistics leave out in-house facilities at universities, hospitals and similar organisations, which CBS estimates used another 142 GWh.

Servers and Sockets: What the Dutch Data Centre Boom Means for Europe's Power Grids - Key statistics


There are also gaps in what is publicly known. An investigation by Trouw and Lighthouse Reports, reported by DutchNews in September, found public energy data for only about a quarter of large Dutch data centres, and reported that grid operator TenneT expects data centres to reach 10 to 15% of Dutch electricity by 2030. That projection is a single-sourced forecast rather than official policy, but it shows how quickly the share could grow.


How the Netherlands compares


On Eurostat figures for 2024 cited by CBS, the Netherlands devoted 4.6% of its electricity to data centres, second only to Ireland at 21.3% and ahead of Germany at 4.2%, Finland at 3.1% and Sweden at 2.1%. By volume, the Netherlands ranks third in the EU behind Germany and Ireland.


Ireland is the clearest example of what happens when data centre growth outpaces the grid. Its Central Statistics Office reported in July that data centres used 7,663 GWh in 2025, 23% of metered electricity, up 10% in a year while all other users grew by 2%. In 2015 the share was 5%. Data centres now use more electricity than all urban households combined. In Dublin, grid operator EirGrid told developers from late 2021 that new data centres in the region were unlikely to be connected until around 2028, and in December 2025 the energy regulator, the CRU, decided that new data centres must bring on-site or nearby generation or storage to match their demand and source at least 80% of their annual consumption from new Irish renewable projects.


Globally, the International Energy Agency estimated in its 2025 Energy and AI report that data centres used about 415 TWh in 2024, around 1.5% of the world's electricity, and projected roughly 945 TWh by 2030 in its base case, driven largely by servers for artificial intelligence. For Europe, the IEA expects demand to rise by at least 45 TWh, around 70%, over the same period. The European Commission, citing the IEA, puts EU data centre consumption at about 70 TWh in 2024.


Why the grid is the bottleneck


The challenge is not only the total amount of electricity but where and when it is needed. Large data centres need big, firm connections, and in the Netherlands those compete with factories trying to electrify, new housing, heat pumps and charging infrastructure. Dutch grid operators laid about 4,500 km of cable and built more than 2,000 transformer houses in 2025, NOS reported, citing Netbeheer Nederland, yet waiting lists for connections continued to grow. In February 2026 the government and grid operators launched a joint plan to speed up connections, and a new prioritisation framework from the regulator ACM took effect in July.


The IEA has noted that grid connection times in parts of Europe now run from two to ten years, and up to seven to ten years in the major hubs of Frankfurt, London, Amsterdam, Paris and Dublin. That is one reason why Europe's share of global data centre capacity has fallen, according to the agency, even as demand grows.


How governments are responding


The Netherlands has chosen to steer location. A pause on new hyperscale data centres was announced in February 2022, and a binding national rule took effect on 1 January 2024. It defines hyperscale sites as those with more than 10 hectares of floor area and a grid connection of 70 MW or more, and allows them only in Het Hogeland, around Eemshaven, and Hollands Kroon, around Middenmeer. Amsterdam and Haarlemmermeer had already paused new permits in 2019 and then capped growth, with Amsterdam requiring new builds to reach a power usage effectiveness of 1.2. The Westpoort campus in Amsterdam, which activists occupied in early November, has drawn criticism because, according to DutchNews, it is split on paper into three smaller facilities.


At EU level the focus is transparency. Under the recast Energy Efficiency Directive and a delegated regulation adopted in March 2024, operators of data centres with installed IT power of at least 500 kW must report a set of energy and sustainability indicators each year to a European database, with results published in aggregate. The Commission has proposed a second step, including a rating label, but it had not been confirmed as adopted at the time of writing.


Turning waste heat into a resource


Almost all the electricity a data centre uses ends up as heat, which is why heat reuse has become part of the policy conversation. The Netherlands Enterprise Agency (RVO) lists Dutch examples: Equinix at Amsterdam Science Park exchanges heat and cold with the University of Amsterdam through underground thermal storage, NorthC supplies a warm-cold network at the High Tech Campus in Eindhoven and is planning heat supply in Aalsmeer, Previder heats an office building in Hengelo, and a data centre on the Mijnwater network in Heerlen supplies heat to offices and a school. These projects are still the exception rather than the rule, and no national figure for the potential is published.


What to watch next


Three things will show whether Europe can absorb this growth. The first is the data: as EU reporting matures and CBS publishes final 2025 figures, it should become clearer how efficiently the largest sites run and how much of their power is matched with new renewables. The second is grid policy: whether the Dutch connection plan shortens queues, and whether Ireland's own-generation rules become a template elsewhere. The third is AI demand: if the IEA's projections hold, data centres will claim a growing share of new electricity in Europe, and the question of who gets connected first will become sharper.


Why it matters

Data centres turn electricity into the digital services everyone uses, but on congested grids every megawatt they take is a megawatt not available to electrify industry, heating and transport. The Dutch and Irish figures show that this is no longer a niche issue: how data centres are located, connected and held to account for efficiency and renewable sourcing is now part of national climate policy.