Croatia's HEP Tenders EUR 480 Million in Works for the Kosinj Hydropower System

Croatia's state power utility HEP has opened a tender to select the contractor for the main civil works and equipment of the Kosinj hydropower system in the Lika region, with the estimated value of works and equipment put at EUR 480 million excluding VAT, according to reports from the Croatian news agency Hina and Balkan Green Energy News on 18 and 19 November.


The tender is being run as a negotiated procedure. Applications are due by 1 March 2027, the indicative start of works is 1 July, and the winning contractor will have 75 months to complete the job. Bids will be scored 90 points on price and 10 points on the length of the warranty, and bidders must lodge a bank guarantee of EUR 14.4 million with their final offer.

Croatia's HEP Tenders EUR 480 Million in Works for the Kosinj Hydropower System - Sustainable Development Goals


The works are substantial. The project would create a reservoir of about 11.45 square kilometres holding roughly 340 million cubic metres of water in the municipality of Perušić, held back by three dams: Kosinj, about 58.5 metres high and 400 metres long; Bakovac, 55 metres high and 450 metres long; and the smaller Sedlo dam at 22.4 metres. A new powerhouse at the Kosinj dam would house turbines of 22 MW and 12.6 MW, and the existing Sklope plant would be upgraded. A replacement road and a diversion tunnel at Bakovac are not part of this tender.


Kosinj is an extension of the Senj hydropower system, which has operated since 1966, and is designed to use the remaining potential of the Lika river, regulate floods in the Kosinj valley and optimise how the whole system runs. Together with the planned Senj 2 plant, the system would reach about 650 MW once complete, more than Zakučac, currently Croatia's largest hydropower plant at 576 MW. HEP obtained the location permit in 2019, has finished the main designs and has applied for building permits.


The value of the project lies as much in timing as in volume. A large reservoir lets operators store water and release it when demand peaks, which is the kind of flexible, low-carbon capacity a grid needs as more solar and wind come online. Croatia has not commissioned a new hydropower plant since Lešće in 2010, so Kosinj would be the first major addition in more than 15 years.


The tender details also show how HEP is weighing cost against durability. Price carries 90 points out of 100, but the remaining 10 go to the length of the warranty, which rewards contractors willing to stand behind dams and equipment designed to operate for many decades. The EUR 14.4 million guarantee required with final bids is meant to filter out bidders without the financial strength to carry a six-year build.


Large reservoirs also bring local costs. Flooding part of the Kosinj valley affects land, homes and ecosystems in Lika, and the project's long history, with planning stretching back years, reflects the time needed for permits and for resettling residents. How HEP manages those impacts will matter as much as the megawatts.


Why it matters

As solar and wind grow, the scarce resource on European grids is flexibility: power that can be dispatched when the sun sets or the wind drops. A reservoir of around 340 million cubic metres feeding a system of about 650 MW gives Croatia exactly that kind of storable, low-carbon capacity, which is why a tender for dams can be read as an investment in the wider renewable build-out.