Jordan Launches Aqaba-Amman Water Carrier as EIB Adds $400m Loan
Jordan has formally launched the National Water Carrier Project, a JD4.68 billion (about $6.6 billion) scheme to desalinate water from the Gulf of Aqaba and pump it to Amman and other cities, the Jordan News Agency (Petra) reported on 18 November. A day later, the European Investment Bank announced a $400 million loan for the project.
Prince Faisal bin Al Hussein, deputising for King Abdullah II, launched the works in Aqaba, with Prime Minister Jafar Hassan attending. Water and Irrigation Minister Raed Abu Saud said the plant will produce 300 million cubic metres of drinking water a year, with delivery expected by the end of 2030. That is about 40 per cent of the country's drinking water needs.

The engineering is substantial. Water will travel through a pipeline of about 417 km and be pumped to around 1,100 metres above sea level. About 300 MW of solar capacity is planned to cover roughly 30 per cent of the project's power needs. The developer Meridiam and the operator SUEZ are building it under a build-operate-transfer model, with ownership passing to the government 26 years after operations begin.
Jordan is one of the most water-scarce countries in the world. According to the ministry, annual water availability per person would rise from about 60 to 110 cubic metres, still far below the 500 cubic metre threshold used to define severe water poverty. Many households currently receive piped water once a week; the ministry expects that to rise to three days a week.
The plant will draw about 600 million cubic metres of seawater a year and return about half to the Gulf of Aqaba. Officials also said the project should free up 150 to 200 million cubic metres a year of treated wastewater for farming in the Jordan Valley, and announced a JD120 million steel pipe plant in Aqaba expected to create about 420 jobs.
On 19 November, the EU and the EIB set out their support. The bank's $400 million project finance loan is backed by an EU guarantee under the European Fund for Sustainable Development Plus. It sits alongside an existing €300 million EIB sovereign loan and €127 million in grants, including €97 million from the EU and €30 million from the Netherlands. A separate letter of intent covers up to €200 million from the EIB and a proposed €50 million EU grant for the national network needed to distribute the water, a project expected to run from 2027 to 2030 and reach around 11 million people. Combined EU and member state financing is estimated at about €1.6 billion.
For Aqaba itself, the project brings construction activity and jobs, but also environmental responsibilities. The Gulf of Aqaba is home to coral reefs that are sensitive to changes in salinity and temperature, so how the plant's return flow of seawater is managed will be watched closely by marine scientists and the tourism sector alike.
Not everyone sees only benefits. Water expert Hazem Nasser told Petra that the cost per cubic metre will be the highest in the history of Jordan's water sector, a reminder that energy-intensive desalination has to be paid for by consumers, the state or both.
Why it matters
Desalination is energy-hungry, and pumping water over 400 km and more than a kilometre uphill adds to that bill. Covering about 30 per cent of the power with solar is a meaningful step, but the remaining energy mix will decide both the project's carbon footprint and how affordable the water is over its 26-year operating period.